| Nature Of Work | Work Preformed for the Units | Type | Duration of Contract in Month: |
|---|---|---|---|
| Instrumentation Work | ETP Plant | Project | 48 Days |
| Occasional Modification of Instruments | Crude, Coker, Hydrogen and Sulfur Plants | Maintenance | 12 Months |
| Occasional Modification of Instruments | Crude, Coker, Hydrogen and Sulfur Plants | Maintenance | 12 Months |
| Instrumentation Field Job | CFP | Project | 4 Months |
| Pre-Commissioning / Commissioning Field Jobs | CFP, Alkylation | Project | 11 Months |
| Instrumentation Pre- Commissiong Jobs at J3 DTA OGBL | OGBL | Project | 24 Months |
| Instrumentation Job at MTF | MTF | Project | 24 Months |
| Instrument Pre-commissioning job at J3 SEZ. PO NO. 260011962 | OGBL | Project | 6 Months |
| Occasional Field Instrumentation Job at J3 PO NO. 186499 | SEZ | Maintenance & Shutdown | 18 Months |
| Instrument Pre-commissioning job at J3 SEZ. PO NO. 260015760 | OGBL | Project | 21 Months |
| Occasional Field Instrumentation Job at J3 PO NO. 260017237 | SEZ | Maintenance & Shutdown | 15 Months |
| Field Instrumentation Job at JMD SEZ PCG Complex PO NO. CCI/260024778 | SEZ PCG J3 | Maintenance & Shutdown | 12 Months |
| Field Instrumentation Job at JMD SEZ PCG Complex PO NO. CCI/260032829 DTD 21.09.2021 | SEZ PCG J3 | Maintenance & Shutdown | 12 Months |
| Field Instrumentation Job at JMD SEZ PCG Complex PO NO. CCI/260032829 | SEZ PCG J3 | Maintenance & Shutdown | On Going |
| Nature Of Work | Work Preformed for the Units | Type | Duration of Contract in Month: |
|---|---|---|---|
| Instrumentation Works | Cyclohaxen Plant | Project | 4 Months |
| Instrumentation Works | IDY Plant | Project | 4 Months |
| Instrumentation Execution Job | FCP Metal Salt Plant | Project | 4 Months |
| Instrumentation Project Activity | R2B Project | Project | 4 Months |
| Instrumentation Job | Meg3 DBN Project | Project | 2 Months |
| Occasional Maint. of Instrumentation | All Units/Plant | Maintenance | 24 Months |
| Occasional Maint. of Instrumentation | All Units/Plant | Maintenance | 24 Months |
| Service Package for Instrumentation Job | SH Recovery | Project | 3 Months |
| Service Package for Instrumentation Job | Propane Plant | Project | 4 Months |
| Instrumentation work during HRSG1 & 2 | SH Recovery | Project | 5 Months |
| Instrumentation work | MEG3 | Project | 9 Months |
| Instrumentation work | MEG3 | Project | 4 Months |
| Instrumentation work for OSBL | Butene-1 | Project | 13 Months |
| Instrumentation work for OSBL Integration | OSBL | Project | 38 Months |
| Instrumentation work | C4HU Area | Project | 7 Months |
| Instrumentation Project work for OSBL Integration | OSBL | Project | 32 Months |
| Instrumentation Project work for OSBL Integration | OSBL | Project | 32 Months |
| Misc. Instrumentation Job in Cracker Shutdown 2014 | Mother plant Cracker | Project | 9 Months |
| Occasional Maint. Of Field Instrumentation | All Units/Plant | Maintenance & Shutdown | 24 Months |
| Occasional Maint. Of Field Instrumentation | All Units/Plant | Maintenance & Shutdown | 12 Months |
| Instrumentation job for Ethane Cracker OSBL area | Ethane Cracker | Maintenance & Shutdown | 6 Months |
| Occasional Maint. Of Field Instrumentation | All Units/Plant | Maintenance & Shutdown | 15 Months |
| Occasional Maint. Of Field Instrumentation | POY/PSF | Maintenance & Shutdown | 15 Months |
| Occasional Maint. Of Field Instrumentation | POY/PSF | Maintenance & Shutdown | 12 Months |
| Occasional Maint. Of Field Instrumentation | All Units/Plant | Maintenance & Shutdown | 12 Months |
| Nature Of Work | Work Preformed for the Units | Type | Duration of Contract in Month: |
|---|---|---|---|
| Instrumentation work | Kirkumbh CPP | Project | 3 Months |
| Nature Of Work | Work Preformed for the Units | Type | Duration of Contract in Month: |
|---|---|---|---|
| Occasional Field Instrumentation Maintenance Job | DMD plants | Maintenance | 14 Months |
| Nature Of Work | Work Preformed for the Units | Type | Duration of Contract in Month: |
|---|---|---|---|
| Instrumentation Job | POY/FDY Plant | Project | 6 Months |
| Instrumentation Job | POY/FDY Plant | Project | 7 Months |
| Instrumentation Project Job | POY/FDY Plant | Project | 5 Months |
| Field Instrumentation Maintenance ARC Works at Silvassa Mfg Complex | All Units/Plant | Maintenance | 12 Months |
| Field Instrumentation Maintenance ARC Works at Silvassa Mfg Complex | All Units/Plant | Maintenance & Shutdown | 12 Months |
| Field Instrumentation Maintenance ARC Works at Silvassa Mfg Complex | All Units/Plant | Maintenance | 12 Months |